Specialized Legal Services

9

Information Technology

9

Investigation

9

Maritime

9

Medical Negligence

SUBMIT YOUR TICKET TODAY!

Services

9

Corporate and Commercial Law

9

Banking & Finance

9

Litigation and Dispute Resolution

Family

9

Marriage, Divorce & Child Custody

9

Inheritance & Wills

Property & Real Estate

9

Buy & Sell

9

Service Charge Claims

9

Rent Dispute & Contract Terminate and invalidate SPA.

SUBSCRIBE

8

On November 6, 2024, the Dubai Court of Cassation issued a noteworthy judgment regarding the enforceability of arbitration clauses in subcontract agreements. This case highlights critical legal aspects surrounding arbitration agreements and the conditions under which they can be deemed valid or void in UAE law. Here, we’ll delve into the main facts of the case, the court’s reasoning, and the practical implications for subcontractors, contractors, and legal practitioners working with commercial contracts.

Case Overview

The dispute arose between two companies engaged in a large infrastructure project in Dubai. The appellant (the subcontractor) had entered into two separate subcontract agreements with the respondents (the contractors) to execute specific project work. These contracts stipulated that a portion of the contract value would be withheld until the completion of the project and the issuance of a handover certificate. Upon completion of the work, the subcontractor requested the release of the withheld payments, arguing that they had fulfilled all obligations and that the contractors were unlawfully retaining approximately AED 1,151,122.81 in contractual payments.

The contractors, however, raised a preliminary objection based on the presence of an arbitration clause in the contracts, which they argued should bar the case from proceeding in court. They contended that the matter was subject to arbitration and that the Dubai Court lacked jurisdiction to hear the case.

Lower Courts’ Rulings

Initially, the Dubai Court of First Instance ruled in favor of the subcontractor, ordering the contractors to pay the withheld amount along with interest. The court rejected the arbitration objection, reasoning that the arbitration clause was not binding due to the subcontractor’s lack of consent to that particular provision. The Court of Appeal later overturned this decision, holding that the arbitration clause was indeed valid and enforceable, thereby dismissing the case on the grounds of lack of jurisdiction.

Court of Cassation’s Decision

The subcontractor appealed to the Court of Cassation, arguing that the arbitration clause was void and unenforceable due to several procedural issues. The main arguments centered around the absence of a clear written agreement to arbitrate and the fact that the arbitration clause was included in the contract’s general conditions, which were not signed by the subcontractor’s representative.

In its November 6, 2024 judgment, the Court of Cassation sided with the subcontractor, ruling that the arbitration clause was indeed invalid. The court emphasized several important legal principles:

Clear Consent Required: Arbitration is a departure from the default judicial process, requiring the explicit and clear consent of both parties. This agreement must be in writing and must demonstrate the intent to arbitrate without ambiguity.

Specificity of Arbitration Agreements: According to UAE law, an arbitration clause must either be signed or explicitly referenced within the contract. In this case, the general conditions containing the arbitration clause were not separately signed or clearly integrated into the main contract.

Principle of Contractual Interpretation: Arbitration clauses must be interpreted narrowly. The court noted that the contractors failed to provide evidence that the subcontractor had explicitly agreed to the arbitration clause. Simply including the clause in ancillary contract documents was insufficient to prove mutual agreement.

Public Policy and Jurisdiction: Arbitration clauses are subject to strict interpretation in UAE courts to ensure that no party is unknowingly waiving their right to seek redress in the courts. The court highlighted that arbitration is an exceptional process and cannot be imposed by inference or implication.

Arbitration Clauses

Legal Analysis

This judgment underscores the UAE’s commitment to ensuring that arbitration agreements meet specific legal standards before they can be enforced. UAE law mandates that arbitration agreements are explicit and in writing, emphasizing the protection of parties’ rights to access the court system unless they have clearly agreed otherwise. This decision reaffirms that arbitration agreements are only binding if they are explicitly agreed upon by both parties, preferably through signatures or unambiguous written references.

Additionally, the ruling demonstrates the Dubai Court of Cassation’s cautious approach towards interpreting arbitration clauses. The decision clarifies that an arbitration clause embedded within general contract conditions may not be enforceable if it lacks the subcontractor’s signature or an explicit reference in the main contractual document. This reinforces the need for contractors and subcontractors alike to clearly define dispute resolution mechanisms to avoid jurisdictional conflicts.

Practical Implications

Drafting Arbitration Clauses: Contractors and subcontractors should ensure that arbitration clauses are clearly stated and signed by both parties. Including such clauses in the main body of the contract or obtaining explicit signatures on attachments that contain arbitration terms is recommended to prevent future disputes.

Clear Consent in Multi-Party Agreements: In multi-party contracts, like those involving contractors, subcontractors, and other stakeholders, parties should explicitly confirm their consent to any arbitration provisions. This avoids misunderstandings about jurisdiction and dispute resolution methods.

Protecting Rights in Subcontract Agreements: Subcontractors should be vigilant in reviewing and negotiating terms in any ancillary contract documents. Understanding and clarifying dispute resolution mechanisms upfront can avoid costly delays and jurisdictional disputes later.

Conclusion

The November 6, 2024 judgment by the Dubai Court of Cassation serves as a landmark ruling on the enforceability of arbitration clauses under UAE law. It highlights the importance of clear, explicit agreements for arbitration and provides crucial insights for contracting parties regarding the rigorous standards that UAE courts apply to arbitration clauses. Contractors, subcontractors, and legal practitioners in the UAE should closely consider this case when structuring and negotiating contracts, ensuring that dispute resolution provisions are both transparent and mutually agreed upon to avoid complications in case of a dispute.

This ruling reinforces that UAE courts will prioritize judicial access and strict contractual interpretation to protect parties’ rights, aligning with the broader legal framework that emphasizes fairness and clarity in contractual relationships.

What you need is having next to you one of the best lawyers in dubai, who is up to date, and knows how to address your needs efficiently and effectively.

Contact Khairallah Advocates & Legal Consultants and benefit from our free 30-min legal consultation.

*Disclaimer: our blogs, law updates, and FAQs are freely distributed for educational purposes and to showcase recent updates and regulations in the UAE’s framework.

If you have any questions and need assistance, contact us at our number or book an appointment online.

Arbitration Clauses